Leasehold Valuation Tribunal                                             LON/00AN/LIS/2008/0023

London Rent Assessment Panel

(transferred from West London County Court)

Landlord and Tenant Act 1985 sections 27A and 20C

 

Address:                                     70 Talgarth Mansions, Talgarth Road, London W14 9DF

 

 

Applicant/ Claimant:                  Daejan Properties Limited (freeholder)

Represented by:                       Mr Petts, counsel

 

 

Respondents/ Defendants:     Mr A F Manso (lessee Flat 70); Mr K Walker (lessee Flat

                                                    73) & Talgarth Mansions Residents’ Association;

Represented by:                        Mr Swabey, solicitor, Swabey & Co

 

Tribunal members:                   Mr T J Powell LLB

                                                     Mr T Sennett FCIEH

                                                     Mr L Packer

 

Date of Transfer from

the County Court:                     14 May 2008

Hearing:                                     9 December 2008 &

                                                    24 February 2009

Decision:                                    2 April 2009


Decisions of the Tribunal

 

(1)          The Tribunal determines that the whole interim demand of £2,143.23 claimed in county court proceedings 7WL02452 is reasonable and payable by the Respondent;

(2)          The Tribunal determines that the whole interim demand of £2,700.00 claimed in county court proceedings 7WL04209 is also reasonable and payable by the Respondent;

(3)          Of the total estimated cost of £519,910.17 for major works, fees and VAT, the Tribunal determines that £498,936.93 is a reasonable interim charge payable by the leaseholders in the respective proportions of their leases.  This decision is effective for Mr Manso, Mr Walker and all leaseholders who are members of the Talgarth Mansions Residents’ Association;

(4)          The Respondent is ordered to refund the £150 Tribunal hearing fee paid by the Applicant within 28 days of the date of this decision;

(5)          An order is made under section 20C of the Landlord and Tenant Act 1985;

(6)          The Tribunal has no jurisdiction over county court costs and fees; 

(7)          This matter should now be returned to the West London County Court.

Background facts

1.             This was an application pursuant to section 27A of the Landlord and Tenant Act 1985 as to the reasonableness and payability of an interim service charge in respect of proposed major works.  The matter began life as two sets of proceedings under Claim Nos: 7WL02452 and 7WL04209 issued by the Applicant Daejan Properties Limited against the Respondent Mr A F Manso, for the sums of £2,143.23 and £2,700.00 respectively, plus interest and costs.  Mr Manso filed defences to those claims which were consolidated and transferred to the Leasehold Valuation Tribunal by order of District Judge Ryan on 14 May 2008.

2.             By the time the Tribunal hearing took place, the sum of £2,143.23 in the first action remained in dispute.  However, of the £2,700 principal claimed in the second action, only £2,150.00 remained in dispute, which sum related to the advance charge in respect of major works. 

3.             Also by the time the Tribunal hearing took place, Daejan Properties had raised two further advance charges for the reserve fund in respect of proposed major works, so that Mr Manso’s total liability for the major works reserve fund was £11,631.  Mr Manso had withheld payment in respect of all of these advance charges for major works. 

4.             By a direction dated 17 September 2008 the Tribunal gave the Talgarth Mansions Residents’ Association and any other lessees not represented by the residents’ association, permission to join in the application.  A request to join the proceedings was received from Mr Karl Walker of Flat 73 and from the Talgarth Mansions Residents’ Association, represented by Mr Christopher Yu, a committee member.

5.             All parties agreed that the Leasehold Tribunal should decide not only the reasonableness and payability of the two interim charges forming part of the consolidated actions transferred by West London County Court, but also of the totality of the interim charges for all of the proposed major works. 

The issues

6.             The interim charges in respect of proposed major works were based upon a specification of works drawn up by Cook Associates on the strength of a two or three page condition survey prepared by the Applicant’s surveyor, Mr Paul Chappel.  Although the specification of works appeared in the Tribunal’s trial bundle, Mr Chappel’s short condition survey was not disclosed to the Tribunal and had not at any stage been disclosed to the Respondents. 

7.             The issues were:

(i)           The Respondents alleged that the consultation procedure under section 20 of the 1985 Act was incomplete and therefore invalid, because Daejan Properties had not given proper reasons for intending to carry out the major works; and

(ii)         The Respondents alleged that the amount of the advance service charges was unreasonable, because the specification of works prepared by Cook Associates was too extensive, and more than the Respondents considered was justified by the condition of the building and by the apparently very brief condition survey, which Mr Chappel prepared. 

The Lease

8.             There was no dispute that the landlord was under an obligation to keep the structure and exterior of the block and the common parts in good repair, nor that the landlord had an obligation to decorate the exterior of the common parts, including the outside doors and door frames, as often as in its opinion was reasonably necessary.  There is therefore no need to recite the lease provisions in this Decision.  There was an issue as to whether the landlord might in the future seek to recharge certain window works to individual leaseholders, but that is not relevant to this determination. 

The Law

9.             Service charges and relevant costs are defined in Section 18 of the Landlord and Tenant Act 1985 (as amended).  The amount of service charges which can be claimed against leaseholders is limited by a test of reasonableness, which is set out in Section 19 of the Act.  Under Section 27A an application may be made to a Leasehold Valuation Tribunal for a determination whether a service charge is payable, including an advance service charge.

10.         The consultation requirements for major works are contained within the Service Charges (Consultation Requirements)(England) Regulations 2003.  The appropriate requirements are those contained in Schedule 4, Part 2.  By paragraph 8(1) the landlord shall give notice in writing of his intention to carry out qualifying works.  By paragraph 8(2) the notice shall … (b) state the landlord’s reasons for considering it necessary to carry out the proposed works.  These provisions form part of what is commonly known as the “Stage 1” procedure. 

11.         The “Stage 2” procedure is contained within paragraph 11.  By paragraph 11(10) “The landlord shall, by notice in writing to each tenant and the association (if any) (a) specify the place and hours at which estimates may be inspected …”

Inspection

12.         The Tribunal members carried out an inspection of the property on the first day of the hearing, 9 December 2008 in the presence of representatives from both parties. 

13.         Talgarth Mansions is a substantial Edwardian mansion block on a narrow and confined site between the busy Talgarth Road (A4) to the front and London Underground railway lines to the rear.  There are 48 flats (of which apparently 21 were owned by Daejan Properties) and 5 front entrances. 

14.         The façade is part-rendered.  The rear and side elevation were largely of brickwork.  Windows are in the main original wood sashes, although some had been replaced.

15.         To the rear, the Tribunal saw open drops to basement areas and extensive cracking to the communal concrete paving. 

The hearing

16.         The hearing commenced on 9 December 2008 and continued on a second day on 24 February 2009.  Daejan Properties was represented by Mr Petts of counsel.  Mr Manso, Mr Walker and the Talgarth Mansions Residents’ Association were represented by Mr Swabey, solicitor.

17.         The Tribunal was provided with a combined Scott Schedule dated 1 July 2008, which identified the items in dispute and which contained both the lessees’ complaints and the landlord’s responses. 

Section 20 consultation

18.         The Respondents disputed the section 20 consultation on the basis that the “Stage 1” notice of intention letter dated 30 April 2007 was inadequate.  That letter set out the major works which the landlord proposed to carry out and stated “the reasons for carrying out these works are in response to a recent survey carried out in addition to the landlord’s obligation to maintain the building in good repair”.

19.         The landlord’s evidence was that the “recent survey” was a document of two or three pages prepared by Mr Chappel following his inspection of the building.  As mentioned above, that condition survey was not disclosed to the lessees, nor was it available to the Tribunal.  

20.         The lessees’ main complaint was that Mr Chappel’s condition survey was insufficiently detailed to justify the very full specification of works which Cook Associates later prepared and upon which various contractors were invited to tender.  More specifically, the lessees complained that if a window survey had been carried out, the lessees would have been better able to comment on the specification of works which followed. 

21.         To an extent, Mr Chappel for Daejan Properties accepted this criticism.  He said in paragraph 3 of his statement “the specification I have prepared is following a basic inspection without high level access equipment, and is based on the current state and condition of the building and what is required to bring the building up to the standard it should be in compliance with the landlord’s obligations under the Lease.  The last works were completed almost a decade ago, so it is not surprising that some of those items need to be renewed or repaired”.

22.         He continued in paragraph 4: “As a result of the limitations of my initial inspection in terms of access to all areas, I have included a number of necessarily provisional items, which will be assessed once the scaffolding has been erected.  It may be that some of the provisional work is not required (whether in part or completely), in which case the contract sum will be reduced to reflect this.”

23.         The Applicants’ case was that Mr Chappel had done the best job that he could from the ground and that he had used his best knowledge and experience to prepare the specification of works, and he confirmed this approach in his oral evidence. 

24.         Mr Laurence Pitts, the surveyor acting on behalf of the Respondents, criticised some aspects of Mr Chappel’s approach, in particular the lack of a windows survey, but in general he endorsed Mr Chappel’s approach.  He had also carried out a ground level survey of the building in order to reach the conclusions set out in his expert’s report.

25.         Mr Swabey, on behalf of the Respondents, laid great emphasis as to the landlord’s lack of consultation with lessees, in its broadest sense, but with regard to the statutory consultation requirements he could only point to the fact that the lessees were not given Mr Chappel’s condition survey, that the freeholder had not carried out a separate window survey and that the reasons in the “Stage 1” notice of intention letter were inadequate. 

26.         With regard to the “Stage 1” letter, there had been a response from the Talgarth Mansions Residents’ Association, albeit out of time.  In its letter of 21 June 2007 the residents’ association indicated which of the planned works were acceptable and also raised some points of contention, upon which it would like clarification.  The letter did not make any mention of Mr Chappel’s condition survey, or complain that the reasons in the “Stage 1” letter were inadequate. 

27.         With regard to the proposed works on the windows and doors, the residents’ association letter stated:

·         Overhaul windows and doors:  In a letter dated 30 May, which was written to Karl Walker (ref: EC/MB), Edward Corrigan stated that only communal areas would be overhauled.  However, in a subsequent letter to Kate West he stated that they were responsible for all windows and doors.  Further clarification is needed on this subject.  In previous years, Freshwater [the property group of which Daejan Properties Limited forms part] replaced windows in communal areas and then consulted individual leaseholders if their windows needed replacing.  Can you confirm that this will be done during the proposed wave of works?

·         Replace windows and doors which are beyond repair:  as above.

·         Refurbish all main entrance doors:  In principal this is agreed, however, the work should be refurbishment of the existing doors in the original style.  Not replacement of the doors.  Redecoration should be in keeping with the overall style of the building.  Refurbishment should include looking at the security of the doors and their locks.”

28.         The letter went on to state that the residents’ association would like another contractor, Mitre Construction Company Limited (“Mitre”), to be considered for the proposed works on the basis that this was the company which had completed the works during the last wave “and we felt they provided an excellent service.”

29.         The letter concluded with these words: “The Residents’ Association is keen for these works to be completed to the highest possible standards and in keeping with the style of the building.”

30.         Even though the residents’ association was strictly out of time to propose Mitre Construction as an alternative contractor, the landlord did seek a quote from that company and, as will be seen, eventually appointed Mitre as the lowest bidder to carry out the works.

31.         The landlord’s “Second Stage” consultation letter was dated 4 March 2008.  This detailed the tenders (estimates), which had been received from four different companies.  As stated, the cheapest tender came from Mitre in the sum of £412,000.00, exclusive of VAT.  The next nearest tender was from Lambourn Contracts in the sum of £435,940.00.  Once the proposed fees and VAT (then at 17½ %) was taken into account, the respective tenders were: Mitre, £540,981.75 and Lambourn Contracts, £572,416.47. 

32.         The letter responded to the residents’ association’s observations by stating: “In response to your enquiries, I can confirm that replacement of windows and doors will be to the common parts only, but as the landlord is responsible for redecoration of the flat windows and if these are beyond reasonable repair, then it will be necessary to include replacement within the scheme and possibly charge back the cost of replacement to the individual leaseholders, this is yet to be clarified.”

33.         The letter went on to say “The original tenders may be inspected at the address stated above [i.e. 51D Oakwood Court, Abbotsbury Road, London W14 8JY] between the hours of 9.30 am and 4.30 pm, Monday to Friday.”

34.         The evidence was that none of the lessees asked to see the original tenders and although also invited to make written observations, no such observations were made. 

35.         As a result of the above, Daejan Properties argued that it had followed the statutory consultation procedures in the 2003 Regulations and had complied with them in every respect. 

The Tribunal’s Decision

36.         Both parties accepted that the landlord has an obligation under the lease to carry out repairs and to maintain and decorate the exterior and common parts.  Seven years had passed since the last cycle of major works in August 2000.  The landlord decided to act now to comply with its obligations under the lease and had appointed an experienced professional, Mr Chappel, to carry out a ground level survey of the building.  That was the express reason given to the lessees in the “Stage 1” letter.  That letter had set out in detail the nature of the proposed works in 12 separate bullet point headings.  At the time, the residents’ association accepted that the work was necessary and did not raise any question about Mr Chappel’s condition survey, upon which the landlord’s proposal was based. 

37.         Mr Chappel accepted that there were limitations to his ground level survey and he acknowledged that a number of items which subsequently appeared in the schedule of works were necessarily provisional. 

38.         The Tribunal is mindful that in this matter it is only adjudicating on estimated charges for major works.  The Tribunal is satisfied that proper reasons were given by the landlord in its “Stage 1” notice of intention letter.  The Tribunal therefore determines that the landlord has complied with the statutory consultation requirements and that therefore there is no breach. 

Items in dispute

39.         At the hearing, the Tribunal was taken through the combined Scott Schedule by the parties.  Generally, each item was dealt with by the parties in order and the Tribunal heard evidence from both parties item by item.  The Tribunal’s determinations therefore follow the same structure as the evidence given.  The Tribunal’s determinations are summarised in the Schedule, which is annexed to this decision.

40.         All of the landlord’s estimated charges for the proposed major works were taken from the tender figures provided by Mitre.  Whatever Mitre had estimated, the landlord sought to charge the lessees by way of an advance service charge to the reserve fund for major works.

1.1       Brickwork/render

41.         The landlord contended for a provisional sum, and therefore an advance charge of £11,600.  The lessees contended that a reasonable advance charge would be £10,750.

42.         The lessees disputed a number of items in the specification of works.  For example, they disputed the need for hammer testing, the cost for repointing and the necessity for general brickwork repairs.  It became clear during evidence that the lessees were working on an incorrect assumption that all the brickwork had been repointed 4½ years ago. 

43.         The landlord’s position was that the specification of works contained provisional areas to be worked upon and provisional costings, all of which were subject to close examination when scaffolding was erected.  For example, until there was scaffolding the landlord indicated that it was uncertain to what extent the brickwork around lessees’ boiler flues would need to be repaired. 

44.         The difference between the parties was minimal in the context of the overall cost of works.  The Tribunal accepts that the landlord’s figures were provisional.  Given that it is adjudicating on an estimated service charge, the Tribunal sees no basis to prefer the fine grained reduction of only £850 proposed by the lessees.  Therefore the Tribunal determines that the figure of £11,600 is reasonable as an estimated charge for this item.

1.2       Stone/concrete cills

45.         The lessees accepted the landlord’s £4,000 estimated charge. 

2.1       External joinery (i.e. repairs to the wooden windows) and

4.0       External redecoration (i.e. all external surfaces and metalwork, including the woodwork of the windows)

46.         Following the tender by Mitre, the landlord made provision for £54,920 for the estimated costs of the external joinery repairs to the windows, plus £64,970 for the estimated cost for the external redecoration (including the windows).  The lessees contended that £64,970 should have been sufficient for both the repairs to the windows and the redecoration of the windows and other exterior surfaces and metalwork.  However, in addition the Respondents’ surveyor Mr Petts allowed an extra £7,000 to cover the estimated cost of those windows which would require more extensive repair works than foreseen by the specification. 

47.         In total, for items 2.1 and 4.0 the landlord sought to collect an estimated charge of £119,890 and the lessees sought to limit the estimated charge to £71,970, the difference between their positions being £47,920.

48.         As indicated above, the landlord’s figures arose from the tender by Mitre.  For the landlord, Mr Petts of counsel emphasised that this was a competitive tender and that overall Mitre’s total estimate was the lowest of four contractors.  The landlord’s position was that it was not appropriate for the lessees to cherry pick between headings in the specification or the tender, because inevitably companies would quote different amounts for different headings.  The landlord justified the separation of items 2.1 and 4.0, because it provided a guide to contractors as to the work that was likely to be needed and then to the surveyor as to the analysis of tenders, and eventually to the supervision of works. 

49.         The Tribunal was invited to compare the figures tendered by Mitre with those of Lambourn Contracts, the next cheapest estimate:

Item

Mitre

Lambourn

2.1

£54,920

£68,066

4.0

£64,970

£47,501

 

£119,890

£115,567

 

The difference between the two tenders was £4,323.

50.         The lessees’ position was that, regardless of the amounts quoted in the tender documents, the specification of works was too detailed and that produced a result that the costs provided for by the contractors were too high.

51.         The Respondents’ surveyor Mr Pitts said that he had carried out an assessment of the building from ground level, using binoculars.  In his view the condition of the windows was not that bad.  In order to assess the likely cost for making good and decorating the sash windows, he relied upon the average costs contained in the Building Cost Information Service (“BCIS”) buildings guideline costs.  That document suggested £175 per item, including infilling, minor and large repairs and decorations.  Mr Pitts calculated that there were 370 items (windows and doors) which required attention, which would give an estimated cost of nearly £65,000.  He said that without the window survey there was no evidence to justify a larger estimate to the cost of this work.  Of the £175 per unit he said that half should be allocated to the cost of overhauling the windows and minor repairs, and half towards redecoration.

52.         Mr Pitts would not accept any of the landlord’s proposed £54,920 for item 2.1, because, he said, the cost of external joinery was included in the £65,970 that he had allowed for both items 2.1 (repairs) and item 4.0 (redecoration).  As indicated above, he did add an additional £7,000 for more significant window repairs, but he considered that all of the other external redecoration work for painted surfaces, metalwork, galvanised metal and rendered surfaces, were minimal or not necessary and should therefore be covered by the £71,970 that he had estimated. 

53.         The Applicant’s surveyor Mr Chappel strongly disputed the approach taken by Mr Pitts.  He pointed out that the BCIS guideline figures were only guides.  He said they needed to be treated with caution and would need adjustment according to the particular property.  Mr Chappel said that there were 390 windows in the building, not 370.  Providing for £175 per item would not allow for the external decorations that might be needed to more than 400 sqm of rendering, to the 69 vertical down pipes at the rear (each 14m in length), to the repainting of the railings at the front, side and rear, or the 240 linear metres of soffits and facias.

The Tribunal’s Decision

54.         The Tribunal had inspected the windows, also from ground level.  In addition, an opportunity was taken to inspect the windows from the inside from one of the common parts stairwells.  Looking at the condition of those windows and with the knowledge that fairly extensive repairs were carried out to them eight or nine years ago, the Tribunal did not consider that the evidence produced by the landlord justified the extent of likely repairs for which the tenders had been invited. 

55.         Considering the reasonableness of the advance charge for these items, the Tribunal takes into account its view of the work likely to be involved.  On the face if it, it does not appear to the Tribunal that such extensive work will be necessary, but the Tribunal does accept that until the scaffolding goes up, it will not be possible to ascertain the actual extent of necessary works.  Overall, the Tribunal considers that the tender figure in item 2.5 is on the high side and a lower figure would be more appropriate.  However, the Tribunal disagrees with the Respondent’s assertion that the £71,970 would be sufficient to cover the extensive painting of the soffits, facias, rainwater goods, metal pipes, railings and rendering.

56.         Assuming there to be 390 windows in the property and assuming that half the BCIS guideline figure of £175 would be allocated to repairs (i.e. £87.50 per window) the Tribunal would allow £34,125, rounded up to £35,000 for item 2.1. 

57.         A similar, if slightly lower figure should be allocated to item 4.0 for the external redecoration of the woodwork and a further £30,000 is considered reasonable for the other painted surfaces.  Therefore, in relation to item 4.0 (external redecoration) the Tribunal confirms the landlord’s estimate of £64,970 as a reasonable advance charge for this proposed work. 

2.2       Doors and Frames

58.         The specification of works allowed for the overhauling of all front doors and the removal of the ironmongery to the front entrance doors and replacements.  In addition, this item allowed for the removal of the existing door and frame to the right hand side of the front elevation and the fixing of a new door.  The estimated cost of this work was £7,400.  The lessees’ position was that the front doors require redecoration, not refurbishment and the ironmongery was in reasonable condition and only needed to be repainted.

59.         The Respondents’ surveyor Mr Pitts had thought at first that the three rear doors to the vault areas had been included in the 2000 works, but when his attention was drawn to the relevant paragraph of the 2000 tender document, he accepted that that work had not been done in 2000.  However, his impression upon inspecting the building was that the front doors only needed decorating, that is they should be rubbed down and repainted, and that this cost should fall within the decorations provision of item 4.0 referred to above.

60.         When the Tribunal inspected the building it considered that some redecoration of the doors was necessary.  At the rear, the Tribunal noted that one or two of the doors were rotten.  The residents’ association had accepted in its letter of 21 June 2007 that the main entrance doors needed to be refurbished (not replaced) and that redecoration should be in keeping with the overall style of the building, in line with its exhortation that the works be completed “to the highest possible standards”. 

61.         In the light of this the Tribunal did not consider that the landlord’s proposal to replace the assorted recent ironmongery was unreasonable.  The Tribunal did not consider the tender estimates for this item were exceptional and therefore determined that the estimate of £7,400 was payable. 

2.3       Soffits and Facias

62.         The landlord sought to charge £3,600 for the proposed work of removing a provisional length of 40 linear metres of soffit boarding and a similar length of facia boarding to the front of the building.  The lessees were unwilling to pay any of this estimated charge.  Mr Pitts said that the gutters and rainwater items were all renewed in 2000.  If the soffits and facias needed doing in 2000, he questioned why they were not done then.  He complained that this proposed work would require taking off the new gutters and rainwater goods. 

63.         Mr Chappel said that it was not easy to see the condition of the soffits and facias from ground level, even through binoculars.  Until they are scraped and checked when the scaffolding is in place, it will not be known how much work might be required.  Since soffits and facias could deteriorate over an eight year period, he had made a provisional allowance to renew limited meterage of some of the facias.  40 metres each represented one-sixth of the total 240 linear metres at the front of the building.

64.         The Tribunal considers that it is prudent to make provision for work to the soffits and facias and determines that £3,600 is reasonable and payable as an estimated charge.

3.0       Rainwater goods/SVP’s/waste pipe work

65.         The landlord had made allowance to remove the provisional length of 25 linear metres of 725 mm diameter cast iron pipe work and 25 linear metres of 100 mm diameter cast iron pipe work, together with associated plumbing work and fixing new galvanised wire cages to all SVP tops.  The provisional estimate for this work was £5,075.  However, the lessees contended that £1,000 would be a sufficient estimate for this work.  This was on the assumption that two or three down pipes might need to be replaced in plastic.  Mr Chappel pointed out that there were some 69 lengths of vertical piping, totalling nearly 900 metres, most of which were in cast iron.  Some of this would need renewing, also in cast iron, which was an expensive process.  He claimed that the £1,000 allowed by the lessees would only cover the cost of replacing one such down pipe.

66.         The Tribunal, upon its inspection, had seen that the guttering was in plastic, but the soil down pipes were generally in cast iron, as were many waste water pipes.  The Tribunal had also seen a number of examples of poor joints and it noted that the residents’ association in its letter of 21 June 2007, accepted that a proper assessment should be made by the contractor about which pipes needed replacing.  The landlord’s estimated cost of £5,075 represented approximately £100 per flat, or to put it another way, an average of £73 per length of pipe, which the Tribunal determines is not unreasonable provision for this type of work.  Therefore £5,075 for item 3.0 is payable by the lessees. 

4.0       External decoration

67.         This has been dealt with above, but in summary the Tribunal allows £64,970 as an estimated charge, of which about half is accounted for by decoration of the windows and the other half for the other surfaces and metalwork under this item. 

5.1       Paving to the rear of the blocks

68.         The tender estimate for this work was £52,500 and the lessees contended that a reasonable estimate would be £31,500.  Mr Chappel said that the approximate area of the paving was 390 sqm. and Mr Pitts suggested it was 360 sqm.  It was agreed between the parties that the approximate area to be covered was about 360 sqm.  It was also agreed that the cracked existing concrete paving needed to be broken up and removed and the whole area resurfaced. 

69.         Mr Pitts relied upon the BCIS average figure of £75 per sqm. for concreting flat areas and calculated the cost as follows: £75 per sqm. x 360 sqm = £27,000; allow £30,000 for this item, to include upstands and kerbs. 

70.         Mr Chappel said that the BCIS figure may well be correct for an unimpeded flat surface, but the rear paving at Talgarth Mansions was on a very restricted site, there was very limited access for plant and the removal of materials, it was a tricky job and he was surprised that the estimate was not higher. He also argued that the estimate tendered by Mitre was competitively priced. 

71.         By comparison, Lambourn Contracts had quoted just under £90,000 for this item.  While the lessees wanted concrete replaced with concrete, in the landlord’s view tarmac was more appropriate, but it required a lot of small edging strips.  However, both experts agreed that tarmac and concrete coverings would cost much the same.   

72.         Having visited the site, the Tribunal accepts Mr Chappel’s arguments that this is a restricted access site and the job would present difficulties.  The Tribunal therefore determined that the provisional sum of £52,500 was a reasonable estimate charge and payable.

5.2/3    Steps and railings

73.         The lessees accepted the cost of repairs to concrete steps.  They also accepted in principle the need to install metal guard rails to the basement voids and fix new mesh panels.  However, the lessees considered that 8 such panels were necessary at £500 each and offered £4,000 for this particular item, rather than the £12,220 proposed by the landlord.  It transpired that there had been some confusion as to what was entailed in the specification.  Mr Chappel clarified that the landlord intended to install 26 panels on 14 sets of stairs (which at £500 each would total £13,000), not 8 panels.

74.         The Tribunal agreed that it was necessary to protect people from falling off the steps and into the basement voids.  It therefore determines that the total estimated charge of £14,170 for this item was reasonable and payable.

6.0       General

75.         The lessees accepted the £189,924 cost of scaffolding preliminaries, general contingency and other items.

7.0       Fees

76.         The lessees accepted the proposed percentage rates that would be used to calculate the fees on the total contract sum.

Summary

77.         As will be seen from the annexed Schedule, as against the grand total proposed estimated cost of works of £519,910.17, the Tribunal determines that some £498,936.93 is reasonable as an advance charge and payable. 

78.         Given that the residents’ association was joined into the Tribunal proceedings, the Tribunal confirms that all leaseholders who are members of the residents’ association, together with Mr Manso and Mr Walker (if they are not also members of the association) benefit from this determination.

79.         In the case of Mr Manso, his share of the approved estimated cost of works (being the “Service Proportion” of 2.15% in the Lease) is £10,727.14, as opposed to the total advance charges for the major works reserve fund in the statement of account dated 8 December 2008 of £11,631. 

80.         In his summing up on behalf of the Respondents, Mr Swabey suggested that the Tribunal had two options.  The first was to say that the interim service charge was unreasonable and the statutory procedure should be carried out again.  For the reasons given above, this option is not appropriate.  His second option was to set an interim service charge at a figure that the Tribunal considers reasonable for the works proposed and that is what the Tribunal has done.  Mr Swabey went on to say that he would ask the Tribunal to recommend that the landlord set up a meeting within 21 days, to take into account the leaseholders’ wishes in relation to the proposed works and to carry out a window survey of the building, including the landlord’s flats. 

81.         The best that the Tribunal can do is to urge the parties to open proper lines of communication, so as to ensure that the eventual works are carried out smoothly, to everyone’s satisfaction and to minimise opportunities for disagreement or dissatisfaction. 

82.         It should be emphasised by the Tribunal that nothing in this Decision affects the leaseholders’ rights to challenge the reasonableness and payability of the final costs incurred, nor the standard of work carried out. 

Costs before the Tribunal and refund of Tribunal fees

83.         On behalf of Daejan Properties, Mr Petts of counsel accepted that there was no provision in the lease to permit the landlord to recover its costs before the Leasehold Valuation Tribunal as a service charge.  He said that the landlord would not object to the making of an order under section 20C of the 1985 Act.  Therefore, for the avoidance of doubt the Tribunal makes an order under section 20C preventing the landlord from recovering its costs of the Tribunal proceedings through the service charge.

84.         Mr Petts confirmed that the landlord had paid £150 as a Tribunal hearing fee and the landlord sought a refund of that fee from Mr Manso.

85.         Regulation 9 of the Leasehold Valuation Tribunals (Procedure) (England) Regulations 2003 allows a Tribunal to order a party to reimburse the whole or part of any fees paid by another party.

86.         The Tribunal noted that the landlord had raised four advance charges for the major works reserve fund for the periods between 25 March 2007 and 24 March 2009, totalling sum £11,631.  Mr Manso had not paid any of those advance charges and it had been his non-payment of the first two that had led to the issue of county court proceedings.  At the Tribunal the landlord was largely successful in justifying the estimated costs of the proposed major works. 

87.         This Tribunal therefore determines that Mr Manso should refund Daejan Properties Limited the sum of £150 within 28 days of this Decision.

The next steps

88.         The Tribunal has no jurisdiction over county court costs and fees.

89.         This matter should now be returned to the West London County Court. 

 

 

 

 

 

Chairman:

 

 

 

Timothy Powell

Date:

2 April 2009

 

 

Annex: Schedule of Estimated Costs determined by the Tribunal as reasonable and payable in respect of proposed major works.

 


LON/00AN/LIS/2008/0023

Annex to Decision

Talgarth Mansions

Schedule of estimated costs determined by the Tribunal as reasonable and

payable in respect of proposed major works.

 

 

Spec

No.

ITEM

Tender £

Lessees’ amount

£

LVT determination £

Consideration

1.0

Ext walls/structures

 

 

 

 

1.1

Brickwork/render

 

 

 

 

1.1.1/2

Hammer test render/ rendering

5000

 

 

 

1.1.3

Pc sum repointing

3750

 

 

 

1.1.4

Pc replace spalled bricks

1350

 

 

 

1.1.5

General brickwork repairs

1500

 

 

 

 

Sub total 1a

11,600

10,750

11,600

 

 

 

 

 

 

 

1.2

Stone/ concrete cills

 

 

 

 

1.2.1

Pc sum for repairs

4000

4000

 

T agrees reasonable

 

Sub total 1b

4,000

4,000

4,000

 

 

 

 

 

 

 

2.0

Ext joinery

 

 

 

 

2.1

Windows

 

 

 

 

2.1.1

(i) Pc sum 12 box sashes

15000

 

 

 

 

(ii) ease adjust sashes

5740

 

 

 

 

(iii) pc replace sash cords

3000

 

 

 

 

(iv) pc replace sash weights

800

 

 

 

 

(v) pc putty

3000

 

 

 

 

(vi) pc lower sashes

9750

 

 

 

 

(vii) a]window repair system

7200

 

 

 

 

        b] pc renew cills

6420

 

 

 

2.1.2

Pc sum additional joinery repairs

4000

 

 

 

 

Sub total 2a

54,920

Incl in 4.0

35,000

 

 

 

 

 

 

 

2.2

Doors & Frames

 

 

 

 

2.2.1/2

Overhaul doors & frames

3000

 

 

 

2.2.3

New ironmongery to front doors

3900

 

 

 

2.2.4

Door & frame to right side alley

500

 

 

 

 

Sub total 2b

7,400

 

7,400

 

 

 

 

 

 

 

2.3

Soffits & Fascias

 

 

 

 

2.3.1

Pc soffit boarding

2000

 

 

 

2.3.2

Pc fascia boarding

1600

 

 

 

 

Sub total

3,600

 

3,600

 

 

 

 

 

 

 

3.0

Rainwater etc goods

 

 

 

 

3.1.1

Replace CI pipework

2675

 

 

 

3.1.4

Pc additional plumbing repairs

1500

 

 

 

3.1.6

SVP terminals

800

 

 

 

3.1.7

Gullies & surrounds

100

 

 

 

 

Subtotal

5,075

1,000

5,075

 

 

 

 

 

 

 

4.0

External redecoration

 

 

 

 

4.1.1

Painted surfaces

 

 

 

 

4.1.2

Metalwork

 

 

 

 

4.1.3

Galvanised metal

 

 

 

 

4.1.4

Woodwork

 

 

 

 

4.1.6

Rendered surfaces

 

 

 

 

 

Subtotal

64,970

71,970

64,970

T sum incl making good & 2.1

 

 

 

 

 

 

5.0

External Works

 

 

 

 

5.1.1-4

Rear paving

51000

30000

 

 

5.1.5

Make good garden areas

1500

1500

 

Not in dispute

 

Subtotal 5a

52,500

31,500

52,500

 

 

 

 

 

 

 

5.2/3

Steps & railings

 

 

 

 

5.2.1/2

Repair concrete steps

750

750

 

T agrees

5.3.1

Repair steps

1200

1200

 

T agrees

5.3.2/3

Metal guard rails/ handrail

12220

4000

 

T £500 per section

 

Subtotal 5b

14,170

 

14,170

 

 

 

 

 

 

 

6.0

General

 

 

 

Not disputed

6.1.1/6

Scaffold

110000

110000

 

 

6.1.7

London Underground costs

15000

15000

 

 

6.2

CDM

2000

2000

 

 

6.4

Prelims

47925

47925

 

 

6.5

General contingency

15000

15000

 

 

 

Subtotal 6

189,925

189,925

189,925

 

 

 

 

 

 

 

7.0

Fees (% of contract sum)

 

 

 

Not disputed

7.1

Cook Associates @ 7%

 

 

 

 

 

Cook Associates CDM @ 0.75%

 

 

 

 

 

Freshwater admin @ 4%

 

 

 

 

 

 

 

 

 

 

 

Cost of major works

 

 

 

 

 

Subtotal 1a

11600

 

11,600

 

 

Subtotal 1b

4000

 

4,000

 

 

Subtotal 2a

54920

 

35,000

 

 

Subtotal 2b

7400

 

7,400

 

 

Subtotal 2c

3600

 

3,600

 

 

Subtotal 3

5075

 

5,075

 

 

Subtotal 4

64970

 

64,970

 

 

Subtotal 5a

52500

 

52,500

 

 

Subtotal 5b

14170

 

14,170

 

 

Subtotal 6

189925

189925

189,925

 

 

Cost of major works (ex fees)

404560

 

388,240

 

 

 

 

 

 

 

 

Cook associates@ 7.75%

31353.40

 

30,088.60

 

 

Freshwater @ 4%

16182.40

 

15,529.60

 

 

 

 

 

 

 

 

Total cost incl fees

452095.80

 

433,858.20

 

 

Vat @ 15%

67814.37

 

65,078.73

 

 

Grand total

519910.17

 

498,936.93