
LONDON RENT ASSESSMENT PANEL
LEASEHOLD VALUATION TRIBUNAL
Case References:
LON/OOAK/LSC/2010/0114 & 0041
Premises at: 25 The
Grangeway, London N21 2HD
APPLICATIONS UNDER SECTION
27A SECTION 20ZA and SECTION 20C of the LANDLORD AND TENANT ACT 1985 (‘the 1985
Act’)
|
Applicants |
Ms Denise Paice and Mr S
Manser (leaseholders) |
|
Representation |
Ms N McNeill and Ms
Catherine Collins (College of Law) |
|
Respondents |
Mr M Peatchey and Mrs D Peatchey (landlords) |
|
Representation |
Mr G Chambers, solicitor
(Gisby Harrison, solicitors) with Mr H Webb, surveyor (WSW Limited,
surveyors) |
|
Hearing Date |
15 and 16 June 2010 |
|
Inspection Date |
15 June 2010 |
|
The Tribunal |
James Driscoll, solicitor
(Lawyer Chair), Luis Jarero BSc FRICS and Clifford Piarroux JP CQSW |
|
Decision Date |
15 July 2010 |
|
The Decision summarised |
Each of the two
leaseholders must pay the sum of £6,414 as a service charge in relation to
the fitting of a new roof. This
represents the figure of £7,148 which they have each agreed to pay with a
deduction of £1,000 each for the poor quality of some of the work. This sum
is exclusive of VAT. The landlord’s application
for an order dispensing with the consultation requirements in section 20 of
the Act and in the regulations made under that provision is refused. |
Introduction
1.
There are two applications. They relate to the subject premises which is
a building consisting of a shop on the ground floor and two flats on the first
and second floors of the building. The
flats are held on long leases. The
owners of the freehold are the landlords under these leases who run a butcher’s
business on the ground floor. We will
call the parties the leaseholders and the landlords respectively. Under the
flat leases each leaseholder must pay one-third of works to the roof of the
building and one half of any works to upper proportion of the structure. The
remainder is paid by the landlord.
2.
We are asked to make a determination of charges made
by the landlords as service charges for major works which were carried out by
fitting a new roof to the building in 2009.
There are a number of complaints by the leaseholders that some of the
works were either faulty or were not completed.
However, the most important and complex of the issues that divides the
parties is whether the landlord carried out the statutory consultation
procedures required by section 20 of the Act and in the regulations made under
that section (the Service Charge Consultation (England) Regulations 2003). According to the leaseholders they failed to
consult properly; the landlords deny this and argue in the alternative that any
breach of the statutory procedure should be excused by the tribunal exercising
its discretion to dispense with these procedures in part of altogether (that is
under section 20ZA of the Act).
3.
It is necessary to summarise the course of the two
applications to the tribunal. First in time were the leaseholders who applied
on 15 February 2010 for a determination of the reasonableness and liability to
pay the charges under section 27A of the Act.
Directions were given for this application at an oral pre-trial review
which was held on 10 March 2010. The
parties appeared at this hearing. The
landlords were represented by their solicitors.
4.
Next came an application by the landlord for a
dispensation from the consultation requirements under section 20ZA of the
Act. Directions were given by the
tribunal on 29 April 2010 supplemental to the directions given in the earlier
pre-trial review. The latter included a direction that the two applications be
heard together.
5.
Two bundles of documents were prepared by the
parties. These included the parties’
statements of case, copies of their leases and copies of documents relating to
the building works. Also included was
copy correspondence and emails passing between the parties.
The Hearing
6. We carried
out an inspection of the premises on the morning of 15 June 2010. Also present were the leaseholders and the
landlord’s solicitor. We inspected the front of the building and the side and
rear of the building. The premises
comprise two flats on the first and second floors above a ground floor
shop. Access to the residential units is
from the rear via a metal staircase. The
front of the building is gabled and is mainly pebble-dash rendered with wooden
shingles between both sets of windows.
The rear elevation is similarly rendered. The building is brick built under a clay
tiled roof.
7.
Ms Paice, Mr Peatchey and his surveyor all gave
evidence. They were cross-examined,
asked questions by the tribunal and re-examined. It soon emerged that the parties agreed on
some the basic facts in the history of this matter. What follows are our findings of the
essential facts of this matter.
8.
Early in 2009 it became apparent that works were
needed to the roof. The landlord sought
advice from his solicitors and his surveyor.
The surveyor carried out an external inspection of the roof but he
relied on a surveyor’s report prepared in February 2008 by a different
surveyor. For health and safety reasons
he could not inspect the roof itself.
This would have involved the erection of scaffolding the expense of
which he thought was not warranted. The
landlord then obtained estimates for the works and he carried out a
consultation exercise himself. (He did not use the correct forms, but the
leaseholders decided not to pursue the argument that this vitiated the validity
of the process). In the event a company
called TSG Building Services Plc were appointed to carry out the works at a
cost of £14,828 which when his fees were added came to a total of £18,927.94.
9.
Scaffolding was erected early in August 2009. Later that month Mr S Walsh of TSG and the
surveyor Mr Webb carried out a close inspection of the roof. It was then apparent that the roof was in a
far worse condition that was originally thought. This led to TSG revising their
contract price. At this point the
landlords started to consider whether it might be more economic to replace the
roof which would be no more expensive that repairs works. This bare summary is as about as far as the
parties agree on the essential facts.
10. Ms Paice
gave evidence and she started by describing the events that led to the first
consultation on the roof works. She said
that the poor condition of the roof had been an issue since 2008. In
undertaking the consultation exercise the landlord used the wrong form of
notice. She was later informed that TSG
had been appointed to do the works under a contract price of £14,828.00. On 23 August 2009 she was notified that the
costs of the work would increase to £35,424.33.
She informed the landlord by email that she did not agree on the works
continuing at this price. She was given
a copy of advice from Mr B Eastern, a Chartered Architect who was asked by Mr
Webb to advise whether the works to the property constituted items that could
be charged to the lessees under the lease.
Mr Eastman confirmed that the works were necessary.
11. At a meeting held on 16 September 2009 between
the parties, the surveyor and Mr Walsh it was not agreed to go ahead with the
works and she says that it was agreed that she would get other quotations for
the work. She managed to get three
quotes but they were all rejected by the landlord acting on advice from Mr Webb. She was given a revised quotation of
£28,688.80 on 5 October and she was concerned of the extra cost of the
scaffolding as the original works could not go ahead. Her neighbour and fellow leaseholder Mr S
Manser mentioned damp to one of the walls to his flat but she does not consider
this to amount to such an emergency as to justify an immediate replacement of
the roof. She did not agree to the works going ahead and she did not receive
the final invoice until 18 January 2010. She has also objected to the
appointment of a project manager for the works as she considers that one of the
inspectors employed by Enfield Council could have been asked to take this
on. She denies that she and Mr Manser
did not want another statutory consultation.
12. Ms Paice also has complaints about the quality
of the works. She has no criticisms of
the works in fitting the new roof though she claims that there were infractions
of the health and safety legislation during the course of the works. The pebble dashing and the ‘barge board’ on
the front of the building are, she complains, of poor quality. Some works to the rear of the building have
still not been completed. She is willing to pay the sum she was properly
consulted on under the first consultation. However, as she has not been
properly consulted over the roof replacement she is not willing to contribute
to these costs. She and Mr Manser also
instructed solicitors (Mr Dutch of Harold Benjamin and Co) to correspond with
the landlord’s solicitors to express their unwillingness to agree to the new
proposed contract.
13. Mr Peatchey gave evidence having signed a
witness statement on 10 May 2010. He
confirmed that he and his wife are the joint owners of the property and the
landlords under the two residential leases.
Early in 2008 he sought his solicitor’s advice and a surveyor’s report
as he had decided that repairs needed to be carried to the roof. Following that advice he consulted the
leaseholders about the proposed works and a preferred contractor was selected. This did not proceed, however, as that
contractor failed to contact him to arrange to start the work. He decided to postpone the work until the
following year.
14. In February 2009 after engaging Mr Webb to
advise, he started another consultation process with the leaseholders as a
result of which TSG Building Services Plc were awarded the contract. He
notified the leaseholders of this appointment and later advised them of the
start date for the works. He describes
how the news that following an inspection the roof was in a far worse state
that was thought originally, shocked him and his wife. The leaseholders made plain their opposition
to the revised contract price. At
the September 2009 meeting he claims
that both leaseholders agreed that time should not be wasted by entering into
another tendering process though they wanted to get their own estimates. As Mr Manser mentioned water ingress into his
flat, there was a common agreement that the works should be started soon and
should not be postponed until the following year.
15. During the
meeting he also suggested that it might be more cost-effective to completely
replace the roof. He says that the leaseholders agreed with this. Mr Webb consulted with Mr Walsh of TSG to
agree a competitive price for the new roof and notified him of the new price on
29 September 2009 and he in turn notified the leaseholders on 5 October
2009. As to the quotes obtained by the
leaseholders he left consideration of that to Mr Webb and his solicitor Mr
Chambers. After receiving their advice he decided to proceed with TSG. He says that it would have been pointless to
conduct another consultation exercise as a result of their agreement on 16
September 2009. Such a process would
have delayed the start date of the work until December 2009. He claims that the
leaseholders did not want to go through a second consultation process.
16. Mr Webb gave evidence having signed a witness
statement on 14 May 2010. He confirms Mr Peatchey’s account of the background
to the 2009 consultation. TSG were
engaged at a quote (with his fees at 10% of the final cost of the works) of
£14,978 for the works to carry out works of repair to the roof. A JCT minor works contract was entered into
on 29 July 2009. A subcontractor put up the scaffolding in August 2009 and
following an inspection with Mr Walsh he asked for a revised price and later
reported to the landlords that the costs had now risen to £27,165.56 (plus
professional fees). As the leaseholders
objected to this a meeting was arranged with them, the landlords and Mr
Walsh. Prior to the meeting he obtained
a second opinion from a Chartered Architect, Mr Eastman who advised, amongst
other things, that the best course was to continue with the existing contractor
(‘with the support of the two lessees’ (paragraph 13 of his statement). Mr Webb added that he had been advised by Mr
Walsh of TSG that they had sought quotes from other roofing contractors but
that the quote they had from their existing sub-contractors was the most
competitive.
17. His account of the September 2009 meeting is
that the leaseholders agreed that there should not be a new consultation
exercise, and it was also agreed that they would seek other quotations.
However, that unless they were so attractive as to make it economic to cancel
the TSG contract that they would stay with this company. Both he and Mr Chambers examined the three
quotations they had obtained and rejected them for various reasons. He was also concerned that TSG would claim a
loss of profit if the contract was cancelled and concerned also at the
additional scaffolding costs. He also
denied any knowledge of health and safety issues and defended the quality of
work which was done.
18. In answer to our questions, Mr Webb told us
that he was shocked when he inspected the roof in August 2009. He confirmed that he has several years
experience in advising as a surveyor on roofs and other major structural work
to buildings. That roof works often
prove more complicated once a full inspection is carried out, it not an
uncommon occurrence, he told us.
However, he said that it would have been impossible to have had a quick
inspection to see the actual state of the roof as temporary scaffolding would
have been required. On the contract with
TSG he told us that he was aware that they subcontracted the works to a roofing
company and a scaffolding company. These
works were supervised by TSG and himself.
In answer to questions about terminating the contract he maintained that
this standard contract could not be terminated without paying TSG damages for
loss of profit. He was unable to show
where this is provided for in that contract.
19. Mr Chambers, in his closing remarks, accepted
that TSG has no direct right to compensation if their contract was
terminated. However, he suggested that
there is an implied contractual right to damages. As to the consultation requirements he
submits that the leaseholders accepted that there should not be a full
consultation when the problems with the roof emerged in August 2009. In answer to our questions he accepted that
the landlord could have had applied either for an advance determination or an
order under section 27ZA in August 2009 but he considered that the landlord and
the leaseholders had agreed on a course of action. Mr Chapman accepted that the statutory
consultation had not taken place.
However, he contended that the landlord and its agents had carried out a
full consultation with the leaseholders and this should persuade the tribunal
to dispense with the requirements exercising our discretion under section 27ZA.
20. Ms Collins made closing submissions on behalf
of the leaseholders. In her submissions,
the consultation requirements should have been strictly adhered to. They exist to protect leaseholders and cannot
be in any sense waived. It would have
been possible to have carried out a consultation and to have started on the
works in good time. She says that the
leaseholders are prepared to pay the amount they originally thought they would
be paying under the formal consultation in the first part of 2009. Reductions should be made from this sum,
however, to reflect the poor quality of some of the work and the fact that the
works to the rear to the property have yet to be completed. She reminded us that the leaseholders do not
consider that they should be in any way responsible for Mr Webb’s fees. She cited various authorities including the
decision of the Upper Tribunal in Daejan
Investments Limited v Benson (and others) [2009] where the landlord’s appeal
against the refusal of a leasehold valuation tribunal to exercise its discretion
to dispense with the consultation requirements in section 20 of the Landlord
and Tenant Act 1985 was dismissed. Lord
Justice Carnwath, the senior president of the Upper Tribunal, stated ‘..The
potential effects - draconian on the one side and a windfall on the other- are
an intrinsic part of the legislative scheme’ (paragraph 40). In that appeal the landlord’s charges were
some £270,000. As a result of their failure to comply in full with the
statutory consultation requirements they could only recover £250 from each of
the five leaseholders.
21. We have decided not to exercise our discretion
to dispense with the consultation requirements in section 20 of the Act. When Mr Webb and Mr Walsh discovered the true
state of the roof it should have been clear to them that an additional
consultation should take place under section 20. Mr Webb admitted during the hearing that a
formal consultation could have been started in August 2009. We have concluded that Mr Webb was committed
to continuing to use TSG as the contractors for the following reasons:
•
he asked Mr Walsh for a fresh quotation for the works
•
he rejected the contractors later proposed by the
leaseholders
•
he arranged for Mr Walsh to attend the September 2009
meeting with the landlords and the leaseholders
•
he failed to contact the scaffolding contractors to
see if they would continue with their provision of the scaffolding if TSG did
not continue with the contract
•
he incorrectly concluded that ending the contract with
TSG would have been costly
•
In that respect, he was wrong to suggest that it is a
term of the JCT contract that TSG would have been entitled to payments for loss
of profits
•
We also reject Mr Chapman’s submission that there is
an implied term in the contract entitling TSG to such payments. It is surely the essence of these widely used
contracts that there is certainty as to the terms of the contract.
22. As the hearing progressed it became clear that
the landlord and those advising them did not seriously pursue the argument that
there had been a proper consultation. It
follows that the real issue is whether the tribunal should exercise its
discretion to dispense with the consultation requirements. Section 20ZA of the
Act reads as follows:
(1) Where this section applies to
any qualifying works or qualifying long term
agreement, the relevant contributions of tenants are limited in accordance with
subsection (6) or (7) (or both)
unless the consultation requirements have been either—
(a)
complied with in relation to the works or agreement, or
(b)
dispensed with in relation to the works or agreement by (or on appeal from) a
leasehold valuation tribunal.
(2)
In this section “ relevant contribution” , in relation to a tenant and any
works or agreement, is the amount which he may be required under the terms of
his lease to contribute (by the payment of service charges) to relevant costs
incurred on carrying out the works or under the agreement.
(3)
This section applies to qualifying works if relevant costs incurred on carrying
out the works exceed an appropriate amount.
(4)
The Secretary of State may by regulations provide that this section applies to
a qualifying long term agreement—
(a)
if relevant costs incurred under the agreement exceed an appropriate amount, or
(b)
if relevant costs incurred under the agreement during a period prescribed by
the regulations exceed an appropriate amount.
(5)
An appropriate amount is an amount set by regulations made by the Secretary of
State; and the regulations may make provision for either or both of the
following to be an appropriate amount—
(a)
an amount prescribed by, or determined in accordance with, the regulations, and
(b)
an amount which results in the relevant contribution of any one or more tenants
being an amount prescribed by, or determined in accordance with, the
regulations.
(6)
Where an appropriate amount is set by virtue of paragraph (a) of subsection
(5), the amount of the relevant costs incurred on carrying out the works or
under the agreement which may be taken into account in determining the relevant
contributions of tenants is limited to the appropriate amount.
(7)
Where an appropriate amount is set by virtue of paragraph (b) of that
subsection, the amount of the relevant contribution of the tenant, or each of
the tenants, whose relevant contribution would otherwise exceed the amount
prescribed by, or determined in accordance with, the regulations is limited to
the amount so prescribed or determined.
23. The party’s recollection of the September
2009 meeting differ in several respects.
The landlords and those advising them suggest that the leaseholders
agreed to waive a formal consultation.
However, we reject the argument (advanced by Mr Chapman) that leaseholder’s
statutory consultation rights can be waived by them.
24. As these statutory requirements were
introduced for the protection of leaseholders it seems to the tribunal that
they cannot simply be excluded except by a prior application to the
tribunal. For example, application
could have been made to this tribunal in August 2009 for an order dispensing
with the consultation requirements or for an advanced determination that the
scope of the works was reasonable. Our
jurisdiction to dispense with the consultation requirements is contained in
section 20ZA to the Act which reads as follows:
(1)
Where an application is made to a leasehold valuation tribunal for a
determination to dispense with all or any of the consultation requirements in
relation to any qualifying works or qualifying long term agreement, the
tribunal may make the determination if satisfied that it is reasonable to
dispense with the requirements.
25. Mr Chapman
suggests that as there was, as it were, a de facto consultation, in the autumn
of 2009. However, we have concluded that
what took place was the very antithesis of both the policy and the detail of
the statutory consultation requirements. We reach this conclusion for the
following reasons: first, the leaseholders were informed of the proposal to
renegotiate the contract with TSG. Those
advising the landlord appeared to have concluded that this was the best way to
proceed from August on and before the leaseholders were told of the additional
costs. Those attending the September
meeting included Mr Walsh of TSG who had a direct interest in the outcome of
the meeting. It was also clear from the
fact that the leaseholders had instructed solicitors that they had grave
misgivings at the way the proposed works had proceeded.
26. Nor are we
convinced that the landlord and those advising them proceeded correctly in February
2009 to commission expensive works without full inspection of the condition of
the roof. Having inspected the premises
we noted that it was possible to have a visual view of most part of the roof
from street level. We also consider
(unlike Mr Webb) that steps could have been taken to carry out a closer
inspection by using, for example, what is commonly known as a ‘cherry
picker’. Unless there was a dramatic
deterioration in the condition of the roof between February and the beginning
of August (which seems highly unlikely) the need for a completely new roof
could have become apparent far sooner than it eventually did.
27. Another way of looking at the situation as is
stood in August 2009 is that a new consultation process could (as Mr Webb
accepted in his evidence) have started that month proposing a new schedule of
works or a new roof inviting the leaseholders to nominate contractors and for
their observations on the proposed works.
If, as seems likely, they would have nominated contractors, it would
have been for those advising the landlords to have sought such estimates and to
have considered them. The process could
have been completed by October 2009 with the appointed contractor starting work
shortly after. The failure to do this
has clearly prejudiced the leaseholders as a more competitive contract could
have been obtained. Mr Webb told us that
TSG use subcontractors and that they add the cost of supervising their work at
a rate between 10 - 15% of the contract costs.
Choosing a suitable contractor who undertakes the work directly could
have been cheaper. Further, by paying TSG for their supervision of the works
and paying Mr Webb’s fees, the leaseholders are, in effect, being charged twice
for the same work.
28. To summarise we have decided not to exercise
our discretion to dispense with the consultation requirements in section 20 and
the regulations made under that section.
We have also concluded that the leaseholders both suffered obvious
prejudice because of the failure to consult properly.
29. We have
some sympathy with the landlords, who, so far as we know are not professional
landlords. They seem to have taken all
the right steps by obtaining professional advice. However, their recovery is subject to the
statutory cap of £250 for each leaseholder.
In this matter, however, the leaseholders have agreed to pay towards the
costs (for works from which they clearly benefit).
30. We turn to the complaints about the quality of
the works. On the basis of our
inspection we have concluded that the pebble dashing was poor and we also noted
that some of the works to the rear of the building have not been
completed. This leads us to the
conclusion that it would be reasonable to deduct £1,000 from the final charges. We explain how we reach our final conclusions
of the amounts payable below.
31. Finally, we
deal with the leaseholder’s objections to bearing any responsibility for Mr
Webb’s fees. We consider that under the
leases the landlords are entitled to appoint agents and to recover their costs. In our view Mr Webb was acting for the
landlords in two capacities: as to their duties under the leases and the Act
and also as individuals who will bear one-third of the costs of the works to
the roof. We do not think it reasonable
to expect the leaseholders to contribute to the landlord’s costs of employing
him. Mr Webb, in our opinion, could have
done far more to investigate the roof in February 2009. We have also concluded that he should have
advised on the need for a fresh consultation in August 2009.
32. The leaseholders told us through their
representatives that they are willing to pay what they originally thought they
would pay that is the total of £14,828.
They did not rely on the statutory cap imposed by section 20. As we have decided to deduct £2000 from this
figure (and not to require them to pay towards Mr Webb’s fees), the
leaseholders are to pay one-half of the net figure of £12,848 which £6,414
each.
33. Finally, there is no need for us to consider
making an order under section 20C of the Act as Mr Chapman told us at the
hearing that the landlords will not seek to recover any of their professional
costs in connection with these proceedings as a service charge.
Signed: ..................................
James Driscoll LLM, LLB Solicitor (Lawyer Chair)
15 July 2010